Gifford St Update and more deals….

It’s been a pretty busy 10 days since I last posted. We closed on a new rehab project on Parker St in Springfield on Wednesday. We also made deals on three new properties; the first is a two family that we are buying from a local money lender, the second is a short sale that we finally got approved after working with Bank of America for almost a year, and the third is an estate property that needs a pretty thorough cosmetic overhaul. 

On top of all that we still have our 6-7 ongoing projects and we will be selling two of our finished properties next week; 37 Mansfield St and 93 White St

Now for our ongoing projects….. Things are moving along well at Gifford St. Most of the rough framing is complete and the plumbers have been there the last couple days doing their rough in. The outside has been completely sided, the new roof is on and we’ve added the new driveway. Heres a look; 

New Driveway

 

New Second Floor Bath framed in with Tub and Plumbing

 

Second Floor Bedroom closet framed in

 

New Second Floor Bedroom with Full Dormer

 

Kitchen looking in from Dining Room

 

First Floor Gutted

 

New Stairway Going In

 

The electricians will be coming in next to do all their rough work once the plumber finishes up. From their we get all our rough inspections done and then it will time to for insulation and sheetrock. Once we get the sheetrock up it will start to look like a house again!!

Comments

  1. Thanks Shawn,

    Glad you like it!!

  2. Shawn Rand says

    WOW! This renovation is absolutely gorgeous. this is exactly why I want to flip homes! This is amazing! Love it.

  3. Keep up the good work guys.

Speak Your Mind

*